- Home
- Departments
- Department of Public Works
- Engineering Division
- Roadway Resurfacing (Paving)
Roadway Resurfacing (Paving)
Click here to view the FY24 and FY25 Paving Plan (roads are subject to change)
Paving Updates
February 1, 2023
The Town will begin its Annual Paving Program in the Spring of 2023. Below you will find a PDF of the list of roadways to be resurfaced and the planned treatment, along with locus maps.
- Annual Paving Program List 2023
- Locus Map 1 - South Tewksbury
- Locus Map 2 - School Street Area
- Locus Map 3 - Jay Street & Crescent Street
- Locus Map 4 - Astle Street
- Locus Map 5 - Pike Street
- Locus Map 6 - Lumber Lane
November 8, 2022
Paving has been completed on Old Boston Road and Astle Street. The Town’s contractor plans to pave Livingston Street and East Street tomorrow, 11/9/2022, and North Street on Thursday, 11/10/2022. Paving work will be conducted from 7:00 AM to 3:30 PM. Days and times of work is subject to change due to weather. Detours maps can be found in the November 7th update.
November 7, 2022
Newport will be paving various roads in Town this week. On Tuesday, November 8, 2022, they plan to pave Astle Street and Old Boston Road. On Wednesday, November 9, 2022, they plan to pave Livingston Street and East Street. Paving work will be conducted from 7:00 AM to 3:30 PM. Days and times of work is subject to change due to weather. Detours maps for each road can be found below.
October 27, 2022
The Town of Tewksbury will start paving projects on Astle Street, Old Boston Road, North Street, East Street and Livingston Street on October 31, 2022. Residents should seek alternate routes over the next two weeks to avoid road closures in these areas. Check the Town's Roadway Resurfacing page under the D.P.W section of the website for project updates. Residents may also call our office at 1-978-640-4440 with questions. Detour maps for each road can be found below.
October 11, 2022
The Town’s contractor, EJ Paving, will complete the top coat of pavement Thursday 10/13 on Livingston Street from Main Street to Wildwood Street (weather permitting) . There will be a detour set up for all through traffic, however, the area will be open to abutters and businesses. Traffic Control Officers will be present to direct traffic for the duration of the work, but delays are likely. We ask travelers to give themselves extra time and thank you in advance for your patience during the work.
October 6, 2022
The Town’s contractor will begin roadway microsurfacing on Tuesday, October 11, 2022 (weather permitting). Microsurfacing is a protective seal coat which extends the life of pavement. It is a thin, tough layer of asphalt emulsion blended with finely crushed stone for traction.
The following roads will be microsurfaced:
- South Elizabeth Street
- South Rhoda Street
- South Amos Street
- Charm Road
- Strang Street
- Patricia Road
Please be advised that roads will have limited access during this time and residents are advised to park all vehicles off the roadway to allow for access by work crews and equipment. Traffic Control Officers will be present to direct traffic for the duration of the work.
Thank you in advance for your patience during the work. If you have any questions or concerns, please contact the Town’s Project Manager, Arthur G. Markos, at 978-640-4440 x237 or by emailing amarkos@tewksbury-ma.gov.
September 30, 2022
The Town's paving contractor, EJ Paving, is completing the top course of pavement on Royal Crest Circle today.
September 21, 2022
The Town’s contractor, Indus, is currently working throughout the town performing crack sealing on the various roads. This is part of the Town of Tewksbury’s overall pavement management program. If you have any questions, please contact the Town’s Project Manager, Arthur G. Markos, at 978 640-4440 x237 or by emailing amarkos@tewksbury-ma.com.
September 19, 2022 Update
Starting Tuesday, September 20, 2022, the Town’s contractor, EJ Paving, will begin road resurfacing work on Livingston Street from Main Street to Wildwood Street. Crews will be working for the remainder of the week. There will be a detour set up for all through traffic, however, the area will be open to abutters and businesses. Traffic Control Officers will be present to direct traffic for the duration of the work, but delays are likely. We ask travelers to give themselves extra time and thank you in advance for your patience during the work. If you have any questions or concerns, please contact the Town’s Project Manager, Arthur G. Markos, at 978-640-4440 x237 or by emailing amarkos@tewksbury-ma.gov.
September 8, 2022 Update
The Town’s Contractor, EJ Paving, will be paving the top coat of pavement on Cayuga Road and Royal Crest Circle on Friday, September 9, 2022. Please be advised that roads will have limited access during this time and residents are advised to park all vehicles off of the roadway to allow for access by roadway paving crews and equipment. Paving is anticipated to begin at approximately 11:30AM on Cayuga Road and will proceed to Royal Crest Circle once completed. If you have any questions or concerns, please contact Andrew Stack at astack@tewksbury-ma.gov or by calling (978) 640-4440, ext. 256.
August 31, 2022 Update
The Town’s contractor, EJ Paving, will begin paving the asphalt berm (curbing) on Royal Crest Circle and Cayuga Road on Thursday, September 1, 2022. Residents are advised to park vehicles off of the roadway during work hours (typically 7:00AM to 4:30PM) to allow for access to the roadway edge by paving crews and equipment. The work is anticipated to begin on Royal Crest Circle approximately mid-morning and will proceed to Cayuga Road once completed. Asphalt berm paving work may extend into Friday, September 2, 2022, if needed. The final roadway surface is to be paved at a later date (to be determined).
August 25, 2022 Update
The Town’s contractor, EJ Paving, will be applying the top final layer of pavement on Old Main Street near Wamesit Island. The work will begin this afternoon and should be completed by the end of the day.
July 26, 2022 Update
The Town’s Contractor, EJ Paving, will be paving the topcoat of pavement on the following roads: Oxford Street, Miles Road and sections of Starr Road and Old Main Street, on Wednesday, July 27, 2022, and Thursday July 28, 2022 (Weather Permitting). Please be advised that roads will have limited access during this time, but traffic control officers will be there to assist if needed. If you have any questions or concerns, please contact The Town’s Project Manager, Arthur G. Markos, by email at amarkos@tewksbury-ma.gov or by calling (978) 640-4440, ext. 237. More Info available at www.tewksbury-ma.gov/paving.
July 11, 2022 Update
The Town of Tewksbury’s contractor, EJ Paving, will begin the process of roadway paving on July 11, 2022 (weather permitting). Work hours will typically be between 7:00 am and 4:30 pm Monday through Friday. Please be advised that roads will have limited access during this time. The entire project will take approximately 2-3 weeks to complete. If you have any sprinkler heads near the roadway please mark out clearly, so that work crews can avoid causing damage.
We appreciate your cooperation and patience in advance. If you have any questions or concerns please contact The Town’s Project Manager, Arthur G. Markos, by email at amarkos@tewksbury-ma.gov or by calling (978) 640-4440, ext. 237.